Project Schedule & Current Status

  • Project Status (Updated Quarterly): Bid phase
  • Construction Start: February 2025
  • Construction End: August 2026
  • Contract Award: Pending

As part the City of Virginia Beach Department of Public Utilities’ Aging Infrastructure Program, the department is replacing the sanitary sewer pump station located at 5721 Susquehanna Drive. The pump station, built in 1959, has reached the end of its useful life. A new pump station will be constructed on the existing site and approximately 300 feet of gravity sewer main will be replaced and realigned. Once completed, the expected service life of the pump station is at least 60 years.