Project Schedule & Current Status

  • Project Status (Updated Quarterly): Major construction complete. Preparing for roadway restoration.
  • Construction Start: Late April 2024
  • Construction End: April 2025
  • Contract Award: $1,463,785.80

The Department of Public Utilities is replacing approximately 2,000 feet of sanitary sewer force main within the southern section of Magic Hollow Boulevard.

Normal working hours will be from 9 a.m. to 4 p.m., Monday through Friday. During construction, there will be noise, temporary changes to traffic patterns, and visible construction equipment and materials staged within the City right-of-way. One lane of Magic Hollow Boulevard will remain open throughout the project, and residents and businesses will have access to their properties at all times.

This project will improve the public infrastructure serving the Magic Hollow neighborhood.