Project Schedule & Current Status

  • Project Status (Updated Quarterly): Active Construction
  • Construction Start: November 2023
  • Construction End: November 2025
  • Contract Award: $8,256,567

Project Description

The Department of Public Utilities is rehabilitating or replacing approximately 14,000 feet of water main lines and 1,600 feet of sewer main lines in the Pembroke Meadows neighborhood. Additionally, 12 fire hydrants will be replaced. 

At the end of construction, the pavement and asphalt within the project area will be fully restored. This project will enhance the reliability of the water and sewer systems serving the neighborhood.

This work is being done as part of the Department's Aging Infrastructure Program.

Pembroke Meadows
Pembroke Meadows project location