Project Schedule & Current Status

  • Project Status (Updated Quarterly): Preparing for construction.
  • Construction Start Date: April 2025
  • Construction End Date: April 2026
  • Contract Award Amount: $2,541,310

The Department of Public Utilities is replacing approximately 2,040 feet of sanitary sewer force main along Central Drive between the pump station at 570 Central Drive and International Parkway. The existing force main, installed in 1992, has reached the end of its useful life and has experienced ongoing issues. This project will improve the public infrastructure serving the area and ensure compliance with state and federal regulations.

This work is being done as part the department's Aging Infrastructure Program

Location map of the improvements