Project Schedule & Current Status

  • Project Status: Under construction - inspection and testing of new pump station followed by demolition of old pump station.
  • Construction Start Date: September 2023
  • Construction End Date: June 2025
  • Contract Award Amount: $2,714,000

The Department of Public Utilities is replacing the sanitary sewer pump station located at 503 Rodney Lane. The 42-year-old pump station has reached the end of its useful life. The new pump station will be located at 505 Rodney Lane and will provide safe and reliable sanitary sewer service for many decades to come.

This work is being done as part of the Department's Aging Infrastructure Program.